Regency Road overpass

Wed., 01 July, 2020

Most of the Regency Road overpass will be assembled ‘off site’ at the Polonia Reserve. The overpass will be constructed in two halves: the northbound, and southbound bridge spans. Each will be 82 metres long and together they will weigh up to 1,310 tonnes.

While the bridge spans are being constructed off site, the on and off ramps, and structures that support the bridge spans, will be constructed at the intersection.

Once assembled, the bridge spans will be transported using Self Propelled Module Transporters (SPMTs) and lowered onto the newly constructed concrete piers.

Fore more information, view the Regency Road Overpass Fact Sheet

Artist Impression of Regency Road overpass – Landscaping shown in mature state

Darlington Upgrade Project – Overpass installation using SPMTs

Partners

  • The Department of Infrastructure, Regional Development and Cities is working with every Australian State and Territory to build much-needed infrastructure across a number of individual funding programs.

    Visit website
  • DPTI works as part of the community to deliver effective planning policy, efficient transport, and valuable social and economic infrastructure.

    Visit website
  • McConnell Dowell is the Creative Construction Company for customers who want to build better communities through safe, smart, efficient infrastructure.

    Visit website
  • Mott MacDonald is an employee-owned management, engineering, and development consultancy with 16,000 staff in 150 countries.

    Visit website
  • An independent firm of designers, planners, engineers, consultants and technical specialists across all aspects of today's built environment.

    Visit website